Madison County road work that may slow your commute: Wall Triana, Pine Grove, Slaughter and more

Roads in several parts of Madison County may be closed for improvement in the next few months.

County commissioners are leading nine road construction projects to help ease high levels of traffic across the county.

They are using the federal American Rescue Plan Act funding from the Biden administration to improve roads. The funding must be used by fall 2026 to access the money, if not, they must use county funds to finish the projects.

  • Patterson Land and Pulaski Pike
    • Move the intersection north approximately 300 yards and install a bridge replacement/culvert extension
    • Start date: March 18, 2025
    • Projected completion time: 275 calendar days
    • Developer: Rogers Group, Inc.
American Rescue Plan Act Madison County construction projectMegan Plotka
  • Wall Triana Highway and McKee Rd
    • Construct a roundabout
    • Start date: July 15, 2025
    • Projected completion time: 120 calendar days
    • Developer: Rogers Group, Inc.
Wall Triana Highway and McKee Rd
American Rescue Plan Act Madison County construction projectMegan Plotka
Slaughter Rd and Eastview Rd
American Rescue Plan Act Madison County construction projectMegan Plotka
Slaughter Rd and Castle Rd
American Rescue Plan Act Madison County construction projectMegan Plotka
Pettus Rd and Pine Grove Rd
American Rescue Plan Act Madison County construction projectMegan Plotka
  • Old Railroad Bed Rd and Lockhart Rd
    • Construct a five-way roundabout
    • Projected start date: Sept. 2025
    • Projected completion time: 275 calendar days
    • Developer: Wiregrass Construction Company
Old Railroad Bed Rd and Lockhart Rd
American Rescue Plan Act Madison County construction projectMegan Plotka
Wall Triana Highway and McKee Rd
American Rescue Plan Act Madison County construction projectMegan Plotka
  • Moores Mill Rd and Countess Rd
    • Enhancing the turn lane so it goes into a “T” shape rather than a curve. It leaves room for turning motions without having to stop
    • Projected start date: Oct. 2025
    • Projected completion time: 275 calendar days
    • Developer: Rogers Group, Inc.
Moores Mill Rd and Countess Rd
American Rescue Plan Act Madison County construction projectMegan Plotka
  • Pettus Road and Nick Davis Road
    • Create turn lanes in four directions and install a turn lane traffic light, because there wasn’t enough room for a roundabout
    • Projected start date: Nov. 2025
    • Projected completion time: 120 calendar days
    • Developer: Wiregrass Construction Company
Pettus Road and Nick Davis Road
American Rescue Plan Act Madison County construction projectMegan Plotka

If you purchase a product or register for an account through a link on our site, we may receive compensation. By using this site, you consent to our User Agreement and agree that your clicks, interactions, and personal information may be collected, recorded, and/or stored by us and social media and other third-party partners in accordance with our Privacy Policy.